Project News

Project Details and the latest information on TCM Civil



Belmont 6 Rising Main

Project finished a couple of weeks over the completion date but overall it was a excellent outcome for our client, Hunter Water Corporation, and TCM.  Dewatering was a major issue but it was addressed by pumps supplied by Vortex.  Environmental concerns were addressed with good site delineation and checking all silt fencing a couple times a day.


Belmont 6 Rising Main

TCM has been awarded the Hunter Water Corporation contract for the Belmont 6 Rising Main. It is the construction of 1,024m replacement section of a sewage rising main (RM) consisting of a 750 mm diameter steel pipeline (DICL with SINTAKOTE finish).  It is720m aerial, 304m open trench.  Construction is expected to be finished in August.