PMHC Area 15 Pipeline & Pumpstation

Port Macquarie Hastings Council

The construction of the sewer pump station and 3 km of rising main for the Camden Haven area.

The infrastructure is required to service the approved 310 home sites future development located within the Camden Haven area.

The works consisted of
  • Construct new DN3800 wet well pumping station
  • Supply and install 3,277m sewer rising main (DN375 DICL)
  • Supply and installation of reclaimed water main (DN110 PE100 PN16)
  • Supply and install buffer tank, stand and associated works
  • Terminate rising main at inlet work

Clarence Town Wastewater Transportation System

Hunter Water Corporation

Completion of remaining works outstanding under terminated contract of former contractor for the construction of Clarence Town wastewater transportation system.

Construction of sewer gravity system.
Construction of 2 wastewater pump stations
Construction of sewer rising mains.

Many challenges were faced after the termination of the previous contractor. Community liaison was paramount to ensure the township of a speedy and professional completion to the project.

After completion of the remaining pipeline and two pump stations, many faults and leakages were found in the sections the previous contractor had constructed that had to be repaired. TCM completed this project with the client and community satisfied with the outcome.