TCM Civil Sewer projects throughout Newcastle, Hunter & Lake Macquarie

PMHC Area 15 Pipeline & Pumpstation

Port Macquarie Hastings Council

The construction of the sewer pump station and 3 km of rising main for the Camden Haven area.

The infrastructure is required to service the approved 310 home sites future development located within the Camden Haven area.

The works consisted of
  • Construct new DN3800 wet well pumping station
  • Supply and install 3,277m sewer rising main (DN375 DICL)
  • Supply and installation of reclaimed water main (DN110 PE100 PN16)
  • Supply and install buffer tank, stand and associated works
  • Terminate rising main at inlet work

Belmont 6 Rising Main Replacement – Stage 2

Hunter Water Corporation

Construction of 1,024m replacement section of a sewage rising main (RM) consisting of a 750 mm diameter steel pipeline (DICL with SINTAKOTE finish.

720m aerial, 304m open trench

56 piles and headstocks

Awaba Waste Management Leachate Pump Station

Lake Macquarie City Council

Part of the expansion of the Awaba Waste Management Facility.  TCM was contracted to construct

    3,412 m of DN140/DN90 HDPE rising main

    Install two new DN160 gravity incoming lines

    1.2m x 1.2m x1.2m flowmeter/dosing pit with trafficable lid and flowmeter

    1.2m diameter actuated valve chamber

    1.8m diameter package pump station with intergral valve 80mm nominal diameter discharge pipework, valves and fittings

Construction of Cardiff Sewermain

Hunter Water Corporation

Upgrade 1 - Construct DN150 gravity sewer main at Orchard & Bent St, Cardiff South
Upgrade 2 - Construct DN375 gravity sewer main at Lachlan Rd, Cardiff
Upgrade 3 - Construct parallel DN150 gravity sewer main at Park Ave, Argenton

Construction of Cardiff Sewermain

Construction of Maryland Gravity Sewer Upgrades

Hunter Water Corporation

Supply and construction of 988 metres of DN525 mm polypropylene diameter gravity sewer

Deep Sewer Contract T-08-01

Port Macquarie Hasting Council

Supply and Construct - 650m 600Ø SewerMax 7m deep.

Deep Sewer Contract T-08-30

Port Macquarie Hasting Council

Supply and Construct - 865m 600Ø SewerMax 5m deep and 1.2m Dia Manholes.

Sewer Reconstruction

Hunter Water Corporation

Supply and Construct - 100m of Deep Complex Sewer Reconstruction through Major Land slip area and 1 Bore under a retaining wall.

Sewerage Upgrade

Nemingah Public School

Supply and Construct - 1650m 63 PE100 Rising Main. Sewerage Pump Station with Switchboard and Odour Control.

The Hill