Construction of Maryland Gravity Sewer Upgrades

Hunter Water Corporation

Supply and construction of 988 metres of DN525 mm polypropylene diameter gravity sewer

Construction of Neath Watermain

Hunter Water Corporation

Construction of 1,272m of 500mm DICL high pressure watermain.
Construction of 66m of 300mm DICL watermain.

Construction of Concrete Slabs for Pumping Station

Eraring Power Station / SNK Group

Construction of 2 concrete slabs for cooling water pumping station and pump workshops. 20m x 10m x 0.6m and 20m x 8m x 0.6m.

Deep Sewer Contract T-08-01

Port Macquarie Hasting Council

Supply and Construct - 650m 600Ø SewerMax 7m deep.

Deep Sewer Contract T-08-30

Port Macquarie Hasting Council

Supply and Construct - 865m 600Ø SewerMax 5m deep and 1.2m Dia Manholes.